Volume and waste
A slab is length × width × thickness; a round hole or column is π × (diameter ÷ 2)² × depth, treated as solid — a post standing in the hole is not deducted. Every dimension is converted to metres first (1 ft = 0.3048 m, 1 in = 25.4 mm exactly), so the cubic metres, litres, cubic feet and cubic yards shown are the same quantity, not separate estimates. The order volume adds your waste allowance to the whole volume; the allowance is yours to set for the job — the page does not assume one.
Where the bag count comes from
Bags = order volume ÷ yield per bag, rounded up, and the page shows the exact quotient and the surplus so the rounding is visible. There is no universal "bags per yard": yield depends on the product and the bag. The ready-made choices quote two manufacturers' own data sheets — QUIKRETE Concrete Mix No. 1101 (40–80 lb bags, data sheet revised October 2022) and Blue Circle Multi-Purpose Concrete (20 kg bag, technical information December 2023) — each labelled by the manufacturer as approximate. For any other product, enter the yield printed on its bag or data sheet. Without a yield, no bag count is shown.
What this does not decide
This is a quantity estimate. It does not choose or check slab thickness, concrete strength, reinforcement, sub-base, footing size, or compliance with any building code — take those from your design or local requirements. Actual yield varies with water, compaction and spillage; delivered ready-mix is usually ordered in supplier increments not shown here. Prices are whatever you enter. Inputs stay in your browser; the same four anonymous usage counts as the rest of the site apply.